OH #2 PROJECT FORD ROAD CIRCUIT Distribution

OH #2 PROJECT FORD ROAD CIRCUIT

Client CenterPoint Energy
Completion Date 2019
Location Indiana

The reconductor of an existing 3PH 12kV overhead distribution underbuild line on the Marrs Road Circuit out of the Mead Johnson Substation. The project included the installation of approximately 12500’ of new 3PH 636 AAC conductor. Additionally, 2740’ of 1/0 AAAC and 3/0 AAAC conductor was installed.